SECTION 306   GENERAL REGULATIONS OF STRUCTURES

                           AND CONSTRUCTION

 

            A.        Required Compliance - No building shall be erected, converted,                                   

                        enlarged, reconstructed, or structurally altered to:  (1) exceed the                                  

                        maximum height; (2) accommodate a prohibited use or house a                         

                        greater number of families; or (3) have narrower or smaller rear,                                   

                        front, or side yards, than are specified herein for the district in which                 

                        such building is located.

 

            B.         Principal Residence - No more than one principal residence shall be

                        permitted on any one lot unless otherwise specifically stated in this                    

                        Ordinance.

 

            C.        Buildings Under Construction Prior To The Ordinance -

                        Nothing in this Ordinance shall be deemed to require any change in the             

                        plans, construction, or designated uses of any building  upon which                   

                        actual construction was lawfully begun prior to the adoption of this                    

                        Ordinance and provided further that such building shall be completed                

                        within one year from the date of passage of this Ordinance.

 

            D.        Temporary Buildings - Temporary buildings or uses for purposes                                  

                        incidental to construction work shall be permitted provided such                                                                                   

                        buildings or uses shall not be continued as permanent structures.

 

            E.         Grading and Seeding  - Proper grading and seeding from the street

                        pavement shall be required of all residential, commercial and industrial

lots.  In the case of a grade of greater than 1 foot for 25 feet of distance                                                                        

from existing pavement, a suitable drain shall be provided, subject to                                                                             

approval by the proper Village authority.

 

            F.         Temporary Parking

 

                        1.   Immediate off-street parking facilities shall be installed within 24                                          

                              hours after foundation or footer digging has been completed.

 

2.   Temporary parking facilities shall not require hard surface or                         

permanent material, but may consist of gravel, stone or other                                                                                                                

suitable material which may be later used as base of a permanent                                          

driveway, or may be later removed.

 

                        3.   Such temporary parking facilities may be located at any suitable

                              place within the side-line and back-line set back of the property,

                              not to interfere with the natural drainage and injurious to

                              adjacent property owners.